Forrest recently completed the installation of 5,200 solar panels across four curved roofs at UU’s Fleetwood waste water treatment works.

We provided an all-inclusive service incorporating:

  • Feasibility study and site investigation
  • Design, supply and install including enabling works
  • Programme / project management
  • Testing and commissioning including G59 connection and REGO accreditation
  • On-going maintenance of the system

 

After undertaking an extensive design and benchmarking process it was decided to use the following specifications as they provided best value and efficiency.

  • ReneSola 250w panels
  • Power One Aurora Plus Inverters
  • Kalzip Mounting System
  • Orsis Smart Meters

 

The project was shortlisted for the Solar Installation of the Year Award 2015 (>1MW) by Solar Power Portal.